Construction of Sahand F-Class Combined Cycle Power Plan has been commenced


The working scope includes the construction of a combined cycle block consisting of one gas unit with the capacity of 307 megawatts and a steam turbine with the capacity of 144 megawatts in ISO conditions (totally 451 megawatts) and 58% efficiency.
Client of Project is Thermal Power Plants Holding Company, MAPNA Group as a Contractor, Ghods Niroo Engineering Company as an Engineering Consultant and Niroo Consulting Engineering Company as a site Supervisor.
Deputy Minister of Electricity and Energy also said at the ceremony: The capacity of Sahand Bonab combined cycle power plant that is 451 MW, will be synchronized at summer 1400. The project is valued at € 250 million and the first fuel of this plant is Gas and the second fuel is gasoline.